September 2024
Work continues on the raft foundation, pool foundation, and western retaining wall, with steady efforts to meet project objectives.
Key Achievements:
- Raft Foundation: Completed over a two-day operation using specialized equipment to ensure accuracy.
- Pool Foundation: Concrete placed to the lower base, demonstrating precise execution.
- Retaining Wall Columns: 17 out of 19 columns poured, enhancing site stability and structural integrity.
Overall Project Completion: 11%
Next Steps:
Weather-Proofing Measures: Apply protective solutions to prevent weather-related delays.
Structural Advancements: Survey and prepare tie beams, optimizing material usage for structural work.
Concrete Operations: Proceed with formwork and pouring for tie beams and additional load-bearing components.