Platinum Developments Villa Construction – Monthly Progress Update September 2024

September 2024

Work continues on the raft foundation, pool foundation, and western retaining wall, with steady efforts to meet project objectives.

Key Achievements:

  • Raft Foundation: Completed over a two-day operation using specialized equipment to ensure accuracy.
  • Pool Foundation: Concrete placed to the lower base, demonstrating precise execution.
  • Retaining Wall Columns: 17 out of 19 columns poured, enhancing site stability and structural integrity.

Overall Project Completion: 11%

Next Steps:

Weather-Proofing Measures: Apply protective solutions to prevent weather-related delays.

Structural Advancements: Survey and prepare tie beams, optimizing material usage for structural work.

Concrete Operations: Proceed with formwork and pouring for tie beams and additional load-bearing components.