Latest Updates and Insights

Stay informed with our latest news and updates.

Platinum Developments Villa Construction – Monthly Progress Update August 2024

August 2024

Advancements included completing the raft foundation and progress on the pool foundation and western retaining wall. The team demonstrated adaptability and focus, ensuring continued momentum toward project goals.

Key Progress:

  • Raft foundation poured over a two-day operation, utilizing specialized equipment for accuracy.
  • Pool foundation advanced with concrete placed to the lower base, highlighting precise execution.
  • Retaining wall columns: 17 out of 19 poured, enhancing site stability.

 

Overall project completion: 11%.

Next Steps:

  • Survey tie beams and continue structural work with optimized material usage.
  • Formwork and concrete pouring for tie beams and additional load-bearing elements.
  • Implement weather-proofing measures to avoid further delays.

Share This Page: