October 2024
Progress was achieved, including pouring of the ground floor slab, cistern, and pool base walls. The team’s efficiency and coordination allowed for significant milestones to be reached, moving the project closer to its goals.
Key Progress:
- Ground Floor Slab: Poured November 6, marking a major structural advancement.
- Pool Base Walls: Poured October 9, setting the stage for pool installations.
- Tie Beams: Gridlines 1-5 completed, providing lateral stability to the structure.
Overall project completion: 32%.
Next Steps:
- Continue work on structural elements, including walls and columns.
- Install floor decks and advance boundary wall construction for site security.
- Prepare for detailed finishing works and initiate material testing for quality assurance.