Platinum Developments Villa Construction – Monthly Progress Update November 2024

November 2024

Advancements this month include the start of superstructure works and final touches on foundational elements. The team emphasized quality control and strategic planning to ensure a seamless transition to the next phases.

Key Progress:

  • Concrete for walls and additional columns completed with precision to meet design specifications.
  • Preliminary landscaping around the site began, creating an organized and efficient workspace.
  • Reinforcement of site logistics to enhance workflow and minimize material handling times.

Overall project completion: 45%.

Next Steps:

  • Begin M&E (first fix phase) to integrate mechanical and electrical systems.
  • Continue with structural and finishing works to meet aesthetic and functional goals.
  • Conduct stakeholder walkthroughs to review progress and address feedback.